A wind turbine photographed from near its base

Coille Beith Wind Farm

Coille Beith Wind Farm is a new wind farm proposal for an area of land south of the River Oykel, and approximately 15km south-west of Lairg.

We are proposing a wind farm with a maximum of 11 turbines with a height of up to 200m to tip. We invite locals and interested parties to come along to our second round of public exhibitions in early April 2025. 

Public Exhibitions

Following our first exhibitions in September 2024, we have been carrying out surveys as part of our Environmental Impact Assessment and amending our designs based on survey results and public feedback. Based on feedback, we have removed the proposed Battery Energy Storage System, reduced the number of planned turbines, and relocated planned turbines.

Visit our public exhibitions in Rosehall or our project website from 2nd April to find out more about the changes we have made.

Location Date & Time
Rosehall Village Hall 2PM - 7PM, Wednesday 2 April 2025
Rosehall Village Hall 10AM - 2PM, Thursday 3 April 2025
Online Wednesday 2 April - Wednesday 16 April

Our Design Iterations

In Summer 2024, we lodged a scoping request with the Energy Consents Unit proposing a maximum of 19 turbines with a height of up to 200m to tip and a Battery Energy Storage System (BESS). 

Following feedback at our public exhibition in September 2024 and the results of surveys carried out as part of our Environmental Impact Assessment, we have removed the BESS and eight of the turbines. We have also made a number of adjustments to the locations of turbines to reduce the landscape and visual impact.

Map showing 11 wind turbines located in an area south of the River Oykel
11 Turbine Project Layout

Project Information

All materials from our September 2024 public exhibition remain available in Project Documents.

Scoping for Coille Beith Wind Farm was submitted to the Scottish Government Energy Consents Unit (ECU) in July 2024 (ref. ECU00005173). All related documents can be found on the ECU website and in our Project Documents section. 

When our proposal is submitted interested parties and statutory consultees will have the opportunity to formally comment on the application. All of the information will be available to view on the Energy Consent Unit’s website and our own project website at the time of submission.

Articles

Picture of a white construction van outside at a windfarm

Find your frequently asked questions here

If you cant find your quesion here, please leave us your question in the form on the bottom of the page and we will give you an answer as soon as we can.  

Read more

Local Suppliers

Our aim is to have the least impact and provide the most benefit to the communities in which we operate. The construction phase is one way we can create economic benefits through inward investment, a...

Read more

Project timeline

  • Stage 1: Site Selection (12 months)

    Extensive research to identify suitable sites. No public engagement is carried out during this time because the site may not pass the criteria required.

     

     

  • Stage 2: Pre-Planning (12 - 18 months)

    Request the view of Highland Council on the level of study required (known as "Scoping"). Sometimes an application for a Met Mast is submitted to measure wind speed at the site.

     
     
  • Stage 3: Submit Planning Application, and Decision (12 months)

    An application is submitted to the Highland Council, accompanied by a comprehensive EIA Report showing the results of all studies undertaken. This is publicly available information.

     

  • Stage 4: Construction (12 - 18 months

    If approved, construction begins at least one year after consent. Construction typically takes 12-18 months and planning conditions are used to manage elements of construction.

     

  • Stage 5: Operation (up to 50 years)

    Turbines are managed by an on-site maintenance team, and operation is controlled by detailed planning conditions. A community fund is active throughout to support worthwhile community initiatives.

     

  • Stage 6: Decommissioning (12 months)

    At the end of the planning period, turbines are removed and the site restored. A financial bond is in place to cover this cost. 

     

The project team

Fraser Clarke
Project Manager
Seumas Skinner
Community Liaison Manager

Learn more about Statkraft and wind power

The history of Statkraft

A short animated video of the History of Statkraft.

Statkraft's History

A deep dive into the vast 125 years of history as Europe's largest renewable energy producer.

Decide Your Future

What kind of world would you choose?

Wind power - how does it work?

Learn how wind generates power.

Did you find what you were looking for?