Field with solar

Stargoose Solar Farm

About Stargoose

Stargoose Solar Farm is a renewable energy project that Statkraft is developing on the Childerley Estate in South Cambridgeshire. The electricity generated by this solar farm will be exported to the National Grid and distributed across the national electricity network to power our homes and businesses. 

Solar projects such as this one will help to end our reliance on fossil fuels, preventing the worsening effects of climate change whilst providing secure and predicable power, helping us to be energy independent, and keeping our bills more stable.

Once operational, Stargoose will not only provide clean energy, a third of the site will be dedicated to biodiversity and landscape improvements, whilst also bringing local investment.

Key figures

  • Solar PV
    Technology
  • 70,000 MWh
    Expected annual electricity generation
  • 29,000
    Equivalent homes powered each year
  • 1/3 of site
    Dedicated to biodiversity and landscape improvements
  • ~£68,000
    Annual community benefit fund

Biodiversity benefits

  • 32% Biodiversity net gain

    32% Biodiversity net gain

    Enhancing biodiversity value of the site

  • 45

    45

    Bird boxes

  • 2

    2

    Owl nest boxes

  • 16

    16

    Bat boxes

  • 900m

    900m

    of new mixed native hedgerow

Project timeline

  • Public consultation

    January 2021

     

  • Planning application submitted

    May 2021

  • Planning approved

    April 2022

     

  • Construction

    September 2026 - 2027/28

     

     

     

  • Operation

    2027/28 - 2064

     

  • Decommissioning

    2064-65

The project team

Gui Zandomeneghi Headshot

Gui Zandomeneghi

Principal Project Manager

Elliot Smith

Construction Project Manager

Rory Puxley

Senior Community Liaison Manager

Did you find what you were looking for?