Wind Farm

Appin Wind Farm

About Appin Wind Farm

 

The proposed Appin Wind Farm is located in Dumfries and Galloway, approximately 6.2 km north of Moniaive and 14.8 km east of Carsphairn.

In May 2025, our Section 36 application for Appin Wind Farm was submitted to the Scottish Government’s Energy Consent Unit, and Additional information was submitted in July 2026 (see Notice below). Our full application can be found under the Planning Application Documents section of our website or on the Energy Consents Unit website (Ref. ECU00003447).

It is proposed that Appin Wind Farm will consist of up to nine turbines, each with a maximum blade tip height of 200 m.

The number of turbines and the height has been reduced following engagement during the scoping process and following feedback from our public exhibitions in 2022. We held our second round of public exhibitions in-person from 17 February to 9 March 2025 to provide the community another opportunity to comment on the Proposed Development.

If the project is consented, it will generate enough electricity to power an estimated 82,000 homes per year, helping Scotland meet its Net Zero emissions target by 2045.

You can view the Public Exhibitions documents, Scoping Request documents in the project documents section. Or find out more about the project by taking time to read our Frequently Asked Questions or by getting in touch.

Project timeline

  • Stage 1: Site Selection (12 months)

    Extensive research to identify suitable sites: positive indicators include good wind speed and minimal environmental and technical constraints. 

     

  • Stage 2: Pre-Planning (6 - 12 months)

    We request the view of the Scottish Government and statutory consultees on the level of study required (known as "Scoping").  

  • Stage 3: Submit Planning Application, and Decision (12 months)

    An application is submitted to the Scottish Government, accompanied by a comprehensive Environmental Impact Assessment Report showing the results of all studies undertaken.  

  • Stage 4: Construction (12 - 18 months)

    If Appin Wind Farm is approved, construction begins at least one year after consent.

    Construction typically takes 12-18 months and planning conditions are used to manage elements of construction.

  • Stage 5: Operation (50 years)

    The turbines are managed from a regionally based maintenance team, and operations are controlled by detailed planning conditions. 

     

  • Stage 6: Decommissioning (12 months)

    At the end of the planning period, turbines are removed. A financial bond, parent company guarantee or another financial instrument is put in place before construction starts to cover this cost.

The project team

Rebecca Todd

Principal Project Manager

Joseph Ogunjobi

Development Comms Manager

Member of

Appin dng logo.jpg

Did you find what you were looking for?