Craig Watch Wind Farm
Craig Watch Wind Farm is a proposed 10 turbine wind farm approximately 8km south of Dufftown on the border of Moray and Aberdeenshire. We are proposing turbines with a tip height of up to 200m, which will have a capacity of approximately 72MW.
Our full planning submission can be viewed on the Energy Consents Unit Website (Ref. ECU00002177) or in the Planning Documents section of this website.
Our Timeline
Our initial proposal for Craig Watch Wind Farm was published in November 2020. We exhibited a 16 turbine layout in March 2021 and a reduced 11 turbine layout in November 2021. Our Section 36 application was submitted to the Scottish Government’s Energy Consents Unit in June 2022.
Between 2022 and 2024, we worked to address feedback from key statutory consultees. This led to the submission of Supplementary Environmental Information (SEI) to the Energy Consents Unit in November 2024. The SEI reduced the number of turbines to ten, removed a proposed Battery Energy Storage System, relocated the substation and optimised the turbine model to take account of improved technology and maximise potential generation capacity.
In May 2026, further Additional Information was submitted to provide an appraisal of a proposed grid connection route. The full grid connection route will be taken forward in a separate application under Section 37 of the Electricity Act. The full public notification of this submission can be found here, including how to view the additional information and how to make representations to Scottish Ministers.