Construction updates

Construction commenced on Neilston Greener Grid Park at the end of August 2023.

Neilston Greener Grid Park will provide stability to the grid with 50MW of batteries and grid stability equipment.

We expect the construction to take approximately 18 months. 

Find out more about grid stability here

Read more about general project updates.

Neilston Greener Grid Park latest construction updates

13 Dec, 2024
Christmas shut down

Construction will stop for two weeks over the Christmas period.

27 Mar, 2024
Neilston Battery Delivery Update.

Delivery of the batteries and inverters for Neilston Greener Grid Park will commence on the 8th April 2024.

26 Feb, 2024
Transformer delivery update

The delivery of the Neilston Greener Grid park transformer (a large piece of electrical equipment which is required for the project to connect to the electricity grid). 

 

20 Dec, 2023
Traffic measures update - Neilston Greener Grid Park

Statkraft will be implementing a temporary 30mph speed limit from the 8 January 2024 to 18 December 2024 on Glenifer Road (the B775) which will cover the duration of the construction of our Neilston Greener Grid Park Project. 

29 Aug, 2023
Construction commences at Neilston Greener Grid Park

Statkraft has commenced construction at Neilston Greener Grid Park.

In April 2022 our planning application for Neilston Greener Grid Park was consented by the Scottish Government’s Department of Planning and Environmental Appeals Division.